    Housing Construction and Employment Generation Program - CYCLE 3

    .

    September 9 - 30, 2005 

    Similar to the increase in completed homes between Cycles 1 and 2, Cycle 3 dramatically intensified the work to generate employment while constructing single-family homes.

     

    Front view of the house when JumpStart stopped the work

                  

    Many of the beneficiaries found out about the housing project through friends, advertisements in the newspaper and on TV. Announcements at various offices also attracted people to ask for our skills and assistance.

     

    Total direct labor costs = $37,657.57

    Total worker days generated = about 4,000 

    Total number of 100 sq meter unfurnished private homes constructed = 16

    A worker putting final touches on a new home 

    Posted at 12:00 am