Renovation work at the Gaza Polytechnic Institute is advancing with all the roofs now completed on the existing buildings.



Floor tiles in two of the buildings have been installed and workers are laying the remainder of the tiles in the other two buildings.


Preliminary plumbing and electrical work has been installed and new ceramic tiles are going up on a number of the interior walls.



1,254 job opportunity days were created in April at the Gaza polytechnic institute site
Renovation work on the Gaza Polytechnic Institute is nearly complete.
With the final inspections now being made, JumpStart’s partner the Community College of Applied Science and Technology, is aiming to begin classes on the new campus this fall.
The four renovated buildings will serve as the foundation for an expanded educational facility providing technical and vocational training for Palestinian students in the Gaza Strip.
The renovation work began in late 2006. Although JumpStart faced several obstacles due to recent political events in the Gaza Strip, we have remained dedicated to honoring our commitment in supporting and assisting communities who strive to advance by their own efforts.