Work site post-excavation and pre-construction in Saba Abkar
Cycle 6 was the second largest cycle of the Housing Construction and Employment Generation project with a total amount spent on labor nearing $30,000. On average, JumpStart International provided 326 job opportunity days for each house construction, while the work on each house lasted an average of 43 days. Beneficiary families were comprised of as many as nine people and as few as three.
Total direct labor costs = $29,054.81
Total worker days generated = about 3,258
Total number of 60 sq. meter unfurnished private homes constructed = 10Total number of 100 sq. meter unfurnished private homes finished = 2
What a tremendous piece of work! This 2-bedroom, 1-bathroom house complements both a spacious living area and kitchen.